AWOL Blade Keeper Bearings!



New board count!

Seems we’re currently on hold - the Blade Keeper Bearings on the Saw Mill decided they wanted to be come independent in multiple pieces. They are on order. Maybe UPS will arrive today........

All of or most of the lumber has been moved directly into the foundation for drying. Stickers cut from old plywood and fiberboard are laid between the layers to allow airflow for the drying process.

Total House Sub-Floor Package requires: 1376 Square Feet

Complete: 1015 Square Feet

In Progress: 361 Square Feet

<><><>

In the wait for UPS, Kevin has had some down time....

He’s been preparing the gardens for winter. We’ve going to have to hot-wire the wire in between our tinker toy conduit fencing. Not much will keep out a hungry deer when they’ve got a craving for pepper plants. They only eat the leaves, JalapeƱo peppers doesn’t suit their palate, :0, but the plants do take offense and don't produce. I was so saddened that I dug up everything this year and now have my garden on the deck. Slower to produce, but ah, the green is so lovely!

From my friends at Olive Forge Herb Farm in Haddock, Georgia, I learned this year that Pepper plants can survive from one year to the next and produce again. I am tickled! Pickled JalapeƱos are one of our favorites.

<><><>

Late breaking news:

Before the Keeper Bearing went AWOL, I learned that there is a good number of boards cut that haven't been counted. We may have already met our Sub-Flooring needs!

Next I believe we will be working on the Roof Package.

~ Cheryl

Wednesday, August 3, 2011

Summer Helper Goes Back To School



Arthur bought a new Nintendo DS this summer from the money he made working with Kevin. He says working the Backhoe is just like another one of his games. He has also decided that manual labor is NOT his future career (Yay!, but he is learning and will keep these skills to enhance his pool of talents.)

He begins 6th grade to day and Kevin will miss his summer helper. It has been a busy summer!

Board cut count has been updated!

Framing Package: COMPLETE!

Board 
Count:                Size:
93                        2x6x10
7                          2x6x12
97                        2x6x8
20                        2x6x16
52                        2x12x17
3                          2x8x16

Sub-Floor Package: Requires 1376 Square Feet ~ 1X6x Random Lengths

Complete: 576 Square Feet

In Progress: 800 Square Feet

~ Cheryl